Bould Farm NFM, nr Bledington
Project at a glance
Completed September 2026
Creation of a large swale, spanning three field parcels, picking up surface water flow paths, reducing flooding in Bledington.
Project status
CompleteArea of focus
After completing a Natural Flood Management Strategy for Bledington, it was highlighted that in high storm events water from the Westcote Brook spilled over into the Bledington Brook catchment. This has increased the pressure on the village brook and has contributed to flooding in the village.
This scheme is aiming to stop this flow between the brook catchments to try and reduce the flooding in the village.
Objectives
The ECP wanted to support the Bledington community, by reducing the amount of flow going through the village. This project increased the amount of water that could be stored across the farm by:
- Excavating a swale across three field parcels, directing high storm flow water across a lower point in the Westcote catchment, away from the perched Westcote Brook.
Outcomes
3 field swale created
Increased water storage reducing flooding downstream in Bledington
Project highlights
Getting to work with new contractors who’s usual work consists of road building, and seeing them enjoy creating more natural forms that blend into the landscape.
Future plans
Continue to monitor the level of the Wetcote Brook to act as an early warning system for flooding in Bledington
Funding
Total cost: £46,231.20 – Funded by Thames Regional Flood and Coastal Committee and the Water Restoration Fund